Redsea Gateway Terminal

For a port terminal in Jeddah Islamic Port North West R4 Berth area in Saudi Arabia, Improvement of an existing revetment was carried out by Saudi Archirodon LTD using Xbloc Armour units. The revetment has a length of 80 m and around 1925 Xbloc units of 0.75 m3 were placed.   

Location

Redsea Gateway Terminal Full View

Project milestones

  • Start of casting: March 2022
  • End of casting: July 2022
  • End of placement: April 2023

Project details

  • Hs = 2.4 m
  • Length of Revetment = 80m
  • Size of Xbloc = 0.75m3
  • Number of Xbloc units = 1925