Tahiti RT2 Faaripo

DMC extended the Xbloc shore protection on both ends which was constructed in 2014. The project in 2022/2023 comprised of 210m of 0.75m3 Xblocs on the Northern side of the main island. Boyer produced and placed the units.  

Location

Tahiti RT2 Faaripo

Project milestones

  • Start of casting: November 2021
  • End of casting: August 2022
  • End of placement: April 2023

Project details

  • Hs: 3.1m
  • Length of shore protection: 210m
  • Size of Xbloc: 0.75m3
  • Number of Xblocs and Xbase: 1825