Georgetown, Saint Vincent

In Georgetown at Saint Vincent a shore protection with a length of 390m has been reinforced with 3,340 Xbloc units of 1m3. The project was started in 2020 and was completed in 2022. 

Location

Georgetown Xbloc

Project milestones

  • First Xbloc produced: 2020
  • Xbloc placement completed: 2022

Project details

  • Size of Xblocs = 1 m3
  • Length of revetment = 390m
  • Number of units = 3,340

More images