Marina Port Forum, Spain

At the Mediterranean Sea coastline of Barcelona in Spain, the existing breakwater of Marina Port Forum is being upgraded. This project is led by Marina Port Forum S.L., Enginyeria Reventos S.L. and Copcisa S.A. The 830 m long breakwater will be reinforced with around 2,600 Xblocs with a volume of 8 m³ as part of the upgrade. 

Location

Casting Xbloc Marina Port Forum

Project milestones

  • Start of casting: February 2025
  • Start of placement: July 2025

Project details

  • Hs = 6.21 m
  • Length of breakwater = 830 m
  • Size of Xbloc =  8 m3
  • Number of units = 2,600

More images