Port of Neom, Saudi Arabia

The Port of NEOM project in Saudi Arabia includes the reconstruction and extension of revetments including the installation of Xbloc units. The size of the units is 2m3 and the total number of units is 1,100 unit. The project consists of three short revetments with a total length of 160m. The production has commenced in 2024 and the last Xbloc unit were placed in May 2025.

Location

Xbloc placement Neom

Project milestones

  • Start of casting: 2024
  • Start of placement: 2024
  • End of placement: 2025

Project details

  • Length of revetment = 160 m
  • Size of Xbloc = 2 m3
  • Number of units = 1,123