Swinoujscie, Poland

At Swinoujscie an LNG terminal is being constructed. The 3 kilometre long breakwater required for this terminal is built by a joint venture of Boskalis, Hochtief, Per Aarsleff and Doraco.

The breakwater consists of a steel cofferdam structure with Xbloc concrete armour on a rock core on the outside.

On the main breakwater Xblocs of 5, 2.5 and 1 m3 are applied. The Xblocs are cast in the port of Swinoujscie.

The Xblocs are transported by barge to the inside of the breakwater and are subsequently placed by hydraulic excavators.

Model testing has been carried out in the laboratory of DMC in Utrecht, Netherlands.

Xbloc underwater placement is assisted by the Echoscope 3D real time sonar. With the Echoscope, the excavator driver is able to see the Xbloc he is placing underwater in real time. Also the previously placed Xblocs are visible on the screen in the drivers cabin in their actual position.

When the Xbloc moves because the lifting chain is pulled out from below the Xbloc, this is visible to the excavator operator. An Echoscope image of placed Xblocs is shown below.

The Xbloc project at Swinoujscie is the third Xbloc project where Xblocs are placed by Boskalis.

Location

Swinoujscie, Poland

Project milestones

Start of casting
August 2011


Trial placement
September 2011


Start placement 1 m3 Xblocs
September 2011


Start placement 2.5 m3 Xblocs
October 2011


Start placement 5 m3 Xblocs
August 2012


Casting completed
October 2012


Placement completed
November 2012

Project details

Hs
4.0 m


Length of breakwater
3 km


Size of Xblocs
1, 2.5 and 5 m3


Number of units
27,500